building-permit-applicationIf you are looking to expand or build a property in Philadelphia, understanding the building permit application process is key. 
A building permit application is necessary for Philadelphia whenever you're making any alterations to a building.

It's not just remodeling, demolitions, or new construction that require a building permit. If you need a certificate of occupancy or installing a new fire system, you need a building permit.

In 2014, the city experienced an increase in the number of residential building permits. In that year, 3973 permits were approved, with an estimated value of $879 million.

If you find applying for a building permit intimidating, keep reading. These are our tips to get your building permit application approved in Philadelphia.

Application Requirements

Once you know what type of permit is needed, it's time to go through the building permit application process. In Philadelphia, permit applications will vary depending on the project.

For example, a new construction has different requirements for an alteration.

With a new construction project, an engineer has to submit a soil investigation report for projects more than 2000 square feet. Alterations usually require flood protection and asbestos information forms.

Most application packages will require a permit application form, a filing fee, three to four sets of plans, and approvals from any related agency.

Every construction, alteration, addition, or demolition project will also require proper signage on site.

How to Get Your Application Approved

There are common errors in permit applications. The most common ones are the number of exits, exterior wall rating, and energy conservation requirements.

Processing Time & Application Fees

Once you submit your building permit application, you will submit an application fee at the same time. The application fee is applied toward the final building permit fee.

The fees range from $25 for 1-2 family homes to $100 for all other properties. You can expect your application to be approved within 15-20 business days.

It will cost you $540.00 to have your application reviewed earlier. The approval process is reduced to 5-10 business days.

Keep in mind that this is in addition to the standard fees and it's not applied toward the final permit fee.

Appeals Process

If you receive a decision and your application is denied, you have 30 days to file an appeal. You are required to fill out an application form along with an appeal application fee.

You will need to work with your contractor or architect to create a compelling case for the appeals board.

After the appeals package is submitted, you'll get a hearing date to appear before the Board of Building Standards.

Hearings are usually scheduled within 4 weeks of receipt of your appeals application.

Take the Guesswork out of the Building Permit Application Process

Getting a building permit can be a daunting process. Once you understand what's required to get the application approved, the whole process becomes less intimidating.

You can choose to have a partner to guide you and take the stress out of the process for you.

Our team can help you with your project from concept to completion. Our team has the expertise to handle the permit application for you.

Contact us today to talk about your next project.

About The Author

Revolutionize your real estate process with the power of Designblendz. Designblendz specializes in architectural design + technologies. We tell stories through for our clients through 3D experiences, powered through 3D visualization and virtually rendered environments through every phase of the design process. These stories are then built into beautiful buildings around the world.